Starbase activities (2025-01-07):
- Jan 6th cryo delivery tally.
- Jan 6th addendum: B14 hot staging adapter is removed. (ViX, Priel)
- Build site: Overnight, S33 is revealed, and the Starlink simulators are loaded. (Mary, ViX 1, ViX 2, ViX 3, Starship Gazer photo, Starship Gazer video, Priel 1, Priel 2, Gisler)
- In the early afternoon, the payload door is closed. (ViX 6x, ViX 3x, ViX real-time)
- S33 aft flap is tested. (ViX)
- S36 tiling in Starfactory continues. (cnunez)
- Launch site: Following the removal of B14 the hot staging adapter, the black LR11000 crane offloads the spreader and straps. (ViX)
- Load spreader is reattached, and the hot staging adapter is lifted back onto B14. (ViX 1, ViX 2, ViX 3, Priel 1, Priel 2, Doherty)
- 1-hour road delay is posted for Jan 8th from 04:00 to 05:00 for transportation from launch pad to factory.
- 1-hour road delays are posted for Jan 8th from 14:00 and 17:00 or Jan 9th from 00:00 to 03:00 for transportation from factory to launch pad (likely S33 rollout).
Flight 7:
- Jan 10th no longer the target date. NET Jan 11th, likely a "3 or 4 days" further. (ViX 1, ViX 2, Cadena OIS (archive), Elon)